Fukushima decommissioning will take at least three decades
2011/10/30
A cover over the Fukushima No. 1 nuclear power plant's No. 1 reactor was completed on Oct. 28. (Tokyo Electric Power Co.)
A draft road map outlining the more than 30-year process of decommissioning and dismantling the crippled reactors at the Fukushima No. 1 nuclear power plant was published by the Japan Atomic Energy Commission (AEC) on Oct. 28.